School Extension - Timeline
February
2021 - Consultation Report
Further to the letter dated 7th December 2020, please note that the consultation period in respect of the above mentioned proposal closed on Monday 18th January 2021
In accordance with the Welsh Government School Organisation Code, the Authority must now publish a consultation report (at least 2 weeks prior to the publication of statutory notice) which:
Summarises each of the issues raised by consultees;
Responds to these by means of clarification, amendment to the proposal or rejection of the concerns, with supporting reasons;
Sets out Estyn’s response to the consultation in full
Responds to Estyn’s response by means of clarification, amendment to the proposal or rejection of the concerns, with supporting reasons.
Please find below the consultation letter and full report
Alternatively, a paper copy can be provided by telephoning 01495 766910 or emailing: mark.horton@torfaen.gov.uk
February
2021 - Cabinet approves plans to expand Crownbridge school
This week, Torfaen Council’s Cabinet committee approved to invest £6,850,000 in a 50 place extension to Crownbridge School.
The extension will be completed by December 2023 and 75% of the investment will be funded by Welsh Government and the remainder funded by the council. The funding is part of the Welsh Government’s 21st Century Schools and Colleges programme.
Crownbridge School is currently oversubscribed with the demand for places expected to increase further. The 50 place extension will be built on the current school site in Croesyceiliog and will help meet the increased demand for special education within the local authority.
Although originally built for 80 pupils, the school currently has 94 pupils and another 21 pupils at Penygarn primary school.
Torfaen’s Executive Member for Education, Cllr Richard Clark said: “The school relocated to its current purpose built accommodation in 2012 for our pupils with severe and profound learning difficulties. The extended facilities for another 50 pupils will give the council the ability to provide places for all foreseeable future applications.
The extension means the council will make savings on external placement than we cannot currently cater for and ensure our learners can have their education within the Borough. We have made plans to ensure disruption to learners on site during construction will be minimised.”
February
2021 - Statutory Pre-Application Consultation
Asbri Planning Ltd. has been commissioned by Tilbury Douglas on behalf of Torfaen CBC to undertake pre-application consultation in respect of Full planning application for the proposed extension to existing school building, relocation of MUGA and associated works at Crownbridge
Summary Info of 2021
Funding
The expansion is expected to cost ÂŁ6.9 million, of which 75 per cent will be funded by the Welsh Government, and 25 per cent by Torfaen County Borough Council.
Current Cost
When students can’t be catered for within the county, some are being sent out to a private provider, which can cost the authority £90,000 a year compared to an in-house cost of £32,000.
Completed
If approved, the project is expected to be completed by December 2023
Savings
The council report says the extra 50 placements would save ÂŁ2.9 million a year if all places were taken up.
November
2022 - Granted Permission For Extension
PLANS to add an extension to accommodate extra pupils at a special school that opened 10 years ago have been given the green light.Â
April
2023 - 3D Model
EPT Partnership came in to show the whole school what our new build is going to look like.
They showed us around the school in 3D.
We saw how the classrooms are going to look.
September
2023 - Build Site Time-lapse
The builders spend our summer working hard clearing land to install the first of the foundations and an access road so they can use bigger and heavier machines
They've sent us a time-lapse showing them starting the construction.
December
2023 - Build Site Time-lapse
You can see them clearing land for the foundation.
They also bring in a crane to lift the heavy beams into place
December
2023 - Frame Going Up
Here's some photos of the foundations and frame going up
January
2024 - The Last Bolt!
We had a ceremony celebrating the last bolt being tightened
March
2024 - Build Site Time-lapse
The frame's complete and the roofs been put on, in theory is should be water tight!
The pupils will be going for an inspection on the last week of term.
We'll be taking lots of photos to look so check back in a few week time.